Furniture Portal Project

 

Detailed Workshop contents, deliverables and timescales

Project kick-off meeting Brussels/CEN 18th July 2000
Workshop kick-off meeting Stockholm Furniture Fair 9th February 2001
Workshop Plenary meeting Open 30 November 2001
Final Workshop Plenary meeting Open January 2002

 

Task Title Workshop Deliverables Dates Edited by
1 Detailed Work Plan

a) Agreed Work Plan
b) Functional document

15/7/00
15/8/00

UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), COSP, Polo Informatica/HI-Cad, Martela Oyj, Unifa, Offma, IMS,
2 End-Users Requirements

a) Information content, Identification and analysis


b) Specification from manufacturers and consumers


First draft guidelines module*

30/9/00

30/10/00

15/12/00

UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo

FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma,

IFF, COSP, Polo Informatica/HI-Cad

3 Site development Plan

a) Test plan for furniture portal

b) WS Kick off and Validation eeting

c) Two Guideline modules

30/12/00

20/2/01

15/3/01

IMS, COSP, Polo Informatica/HI-Cad

UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo

FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma

4 Search Engine, Web Page and Internet Design

a) Adaptation of a Search Engine
Suitable Website

30/3/01
15/5/01

UEA, FEMB, IMS, COSP, Polo Informatica/HI-Cad

5 Target Data Input

a) Sites data input
b) Self-Registration System

30/5/01
15/7/01

UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IMS, COSP, Polo Informatica/HI-Cad
6 Implementation of site

a) An operational site
b) Control Panel and Evaluation System
c) System Validation

30/7/01
18/8/01
15/9/01

UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IMS, COSP, Polo Informatica/HI-Cad
7 Demonstration and assessment

a) Dissemination of the project
b) Impact of the project and
c) Organization of the Cen Workshop
d) Dissemination actions and follow-up
e) Final Report

30/9/01
15/10/01
30/11/01

15/12/01

15/1/02

UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IMS, COSP, Polo Informatica/HI-Cad
* Workshop deliverables are marked in red

 

Resource requirements

30 man-days have been assigned to workshop management, as a large amount of time must be spent organizing concentration activities.