CEN/ISSS Workshop
Furniture Portal Project
Detailed Workshop contents, deliverables and timescales
| Project kick-off meeting | Brussels/CEN | 18th July 2000 |
| Workshop kick-off meeting | Stockholm Furniture Fair | 9th February 2001 |
| Workshop Plenary meeting | Open | 30 November 2001 |
| Final Workshop Plenary meeting | Open | January 2002 |
| Task | Title | Workshop Deliverables | Dates | Edited by |
| 1 | Detailed Work Plan |
a) Agreed Work Plan |
15/7/00 |
UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), COSP, Polo Informatica/HI-Cad, Martela Oyj, Unifa, Offma, IMS, |
| 2 | End-Users Requirements |
a) Information content, Identification and analysis
|
30/9/00 30/10/00 15/12/00 |
UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IFF, COSP, Polo Informatica/HI-Cad |
| 3 | Site development Plan |
a) Test plan for furniture portal b) WS Kick off and Validation eeting c) Two Guideline modules |
30/12/00 20/2/01 15/3/01 |
IMS, COSP, Polo Informatica/HI-Cad UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma |
| 4 | Search Engine, Web Page and Internet Design |
a) Adaptation of a Search Engine |
30/3/01 |
UEA, FEMB, IMS, COSP, Polo Informatica/HI-Cad |
| 5 | Target Data Input |
a) Sites data input |
30/5/01 |
UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IMS, COSP, Polo Informatica/HI-Cad |
| 6 | Implementation of site |
a) An operational site |
30/7/01 |
UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IMS, COSP, Polo Informatica/HI-Cad |
| 7 | Demonstration and assessment |
a) Dissemination of the project |
30/9/01 15/12/01 15/1/02 |
UEA, Medifa, ANIEME, SMI, CBM, AFFJI, APIMA, VDM, Assarredo, FEMB, Assufficio, Assufficio - (Brussels Branch), Martela Oyj, Unifa, Offma, IMS, COSP, Polo Informatica/HI-Cad |
| * Workshop deliverables are marked in red | ||||
Resource requirements
30 man-days have been assigned to workshop management, as a large amount of time must be spent organizing concentration activities.